I am trying to switch out the concrete footings for screw piles but I can't find a ground screw option anywhere. Can anyone shed some light on this?!

Thank you!

Share this post


Link to post
Share on other sites

Thank you SO much. Do you know how to actually place those ground screws? I was hoping there was an option to replace concrete footings with ground screws but looks like I may have to do it manually - im having a hard time lining up the posts and screws. If that makes sense?

Sorry I'm new here!

Share this post


Link to post
Share on other sites

I don't think he got a problem he is asking if footings can be replaced with helical screw piles and if any available in the library. 

  • Like 1

Share this post


Link to post
Share on other sites
1 hour ago, Mjfurgs said:

Thank you SO much. Do you know how to actually place those ground screws? I was hoping there was an option to replace concrete footings with ground screws but looks like I may have to do it manually - im having a hard time lining up the posts and screws. If that makes sense?

Sorry I'm new here!

I know how in real and I know how in Chief Architect! If you can, please post a screenshot your showing your issue. It'll make it easier to point out a solution.

Share this post


Link to post
Share on other sites
9 hours ago, Mjfurgs said:

Thank you SO much. Do you know how to actually place those ground screws? I was hoping there was an option to replace concrete footings with ground screws but looks like I may have to do it manually - im having a hard time lining up the posts and screws. If that makes sense?

Sorry I'm new here!

 

You may have to do it manually.

Screw Piles may be found in the 3D Warehouse, for download.

They are Sketch Up files but Chief Architect will open them and add then to the library

 

750071670_ScrewPile.thumb.PNG.3458637088b01269944a6b9c7d01272a.PNG

 

Model here

  • Like 1

Share this post


Link to post
Share on other sites

You need to manually place them, but I would leave the Auto Deck on until you are certain you are ready to place the piles. That way all the deck posts and beams will be in place and it's just a simple matter of deleting the concrete footings and replacing them.

 

No need to know what your computer or software is, just a simple answer to a simple question.

 

  • Like 1
  • Downvote 1

Share this post


Link to post
Share on other sites
4 hours ago, joey_martin said:

No need to know what your computer or software is, just a simple answer to a simple question.

 

The guys above are just trying to be helpful and get people started off on the right foot.  Example?  The following statement would make absolutely no sense and would serve no purpose but to confuse for a person using HD Suite...

 

4 hours ago, joey_martin said:

but I would leave the Auto Deck on until you are certain you are ready to place the piles.

 

 

  • Like 1

Share this post


Link to post
Share on other sites

I figured it out!

Thank you everyone for your combined efforts in helping this newbie!

I'm sure I will be back for more!

Cheers

Share this post


Link to post
Share on other sites

Please sign in to comment

You will be able to leave a comment after signing in



Sign In Now

  • Member Statistics

    27613
    Total Members
    6254
    Most Online
    3dvfxarch
    Newest Member
    3dvfxarch
    Joined