ACADuser Posted March 3, 2017 Share Posted March 3, 2017 I used a "Doorway" and added a Barn Door (Surface Sliding Door Arch Block) to the plan. Now I need to include it in the schedule but it appears as though Doorways are not included in the Door Schedule, Period. I have "Include in Schedule" checked. Link to comment Share on other sites More sharing options...
Dermot Posted March 3, 2017 Share Posted March 3, 2017 You can check "Doorways" in the "Objects to Include" section of the schedule specification dialog. Unfortunately, if you are using X8 and prior, there is no easy way to modify the doorway so that it will show up as a barn door in the door schedule. This is because there is no actual object for the doorway listed in the components dialog. If you are using X9, you can select the doorway and modify the Object Information to control what information appears in the schedule. Link to comment Share on other sites More sharing options...
Joe_Carrick Posted March 3, 2017 Share Posted March 3, 2017 Actually, you can use the OIP to include a Comment and/or addition to the Description for that Doorway. Link to comment Share on other sites More sharing options...
DRAWZILLA Posted March 3, 2017 Share Posted March 3, 2017 I use the description and comment sections to add notes and the wording I need Link to comment Share on other sites More sharing options...
ACADuser Posted March 20, 2017 Author Share Posted March 20, 2017 Had to use this again today, Thanks for pointing the way. Link to comment Share on other sites More sharing options...
BeaconHill Posted May 11, 2017 Share Posted May 11, 2017 I also am adding specs for a barn door and am looking to add info in the schedule. I have added doorways to the schedule dbx. However, for some reason, when I try to modify the comments or description of a doorway in the Components dbx, it does not show the changes in the schedule. Any thoughts? I have used plain txt over the schedule as a work around, but if the schedule changes, I will have to remember to check on it. Link to comment Share on other sites More sharing options...
Joe_Carrick Posted May 11, 2017 Share Posted May 11, 2017 Are you using X9? If so, you should use the OIP fields in the Door dbx. Then add the appropriate Column(s) to the Door Schedule. The above won't work in X8 or prior. Link to comment Share on other sites More sharing options...
GeneDavis Posted May 11, 2017 Share Posted May 11, 2017 But won't the Joe Carrick idea of using an invisible wall and a pocket door for doing the barn slider work? That, and a few p'line solids to model up the track and wheels, and it's a wrap. Oh, and on the schedule, too. Link to comment Share on other sites More sharing options...