MarkMc 532 Posted April 21, 2016 Can't figure out what is going on. Plan originally from X7 (could even be 6) but has been worked on in every iteration of X8 before and may have been copied and pasted into a new x8-dunno. It is from before I started to place schedules into CAD details. Anyway. Opened it up to do a small edit and see that I have overlapping callouts on plan and elevations. Each cabinet has two callouts-they are not the same numbers but the schedule doesn't show extra numbers. Place a new object and get two callouts both with the same number on it? Go to the schedule for the kitchen -big one on left- open, change to any other room-extra callouts go away? Thought maybe I'd made a detail from view by accident except that it happens on newly placed objects. Any idea what I did?? I've rummaged through old save as and the archives and found a point where I can rebuild this from-not too bad once I figure out what needs to change. Already sent it in to support. Really hoping not to have to wade through this an older plan though. This one has been more changes than.... double schedule.zip Share this post Link to post Share on other sites
Alaskan_Son 2458 Posted April 21, 2016 You just have 2 schedules Mark. One in the plan, and one in a CAD Detail labeled "Schedules"...and they're both set to Use Callout For Label. Share this post Link to post Share on other sites
Joe_Carrick 2313 Posted April 21, 2016 Yep, you just need to find the second Schedule and delete it. It could be anyplace in the Plan (Floor, Elevation, Section, CAD Detail, etc) Share this post Link to post Share on other sites
MarkMc 532 Posted April 21, 2016 I think the second one got there when I was testing Larry's copy paste problem (didn't crash). Didn't realize I saved it duh Share this post Link to post Share on other sites