This is a recent issue in X13 premier. I have found a need to create a separate default set to handle layer settings for 3D Elevation view versus a plan view. I needed to show Electrical in the 3D view. When I created the separate default set, For the SAME schedule of Bath Notes, I got this result. The Default sets are used respectively for a plan view at 1/2" scale AND a 3D view at 1/2" scale with only a change in displaying electrical. Does anyone know about this anomaly and why the Notes are getting double numbers? Again, there is only ONE schedule referencing the placed custom Notes.

 

Thank you for the assistance.

22-0201-BAth Notes show duplicate numbers-PLAN.jpg

22-0201-BAth Notes show duplicate numbers-ELEV.jpg

22-0201-BAth Notes show duplicate numbers-schedule.jpg

Link to comment
Share on other sites

  • Solution

To All... I figured it out. In the Project Browser under the list of Schedules, there was a second schedule created that used the SAME Note assignment. In my Case it was a Custom Note Style called "Bath Notes". Once I deleted this extra schedule from the list, the Notes updated with a SINGLE number.

22-0201-SOLVED-BAth Notes show duplicate numbers-ELEV.jpg

22-0201-SOLVED-BAth Notes show duplicate numbers-schedule.jpg

Link to comment
Share on other sites

Renerabbitt,

 

Could you elaborate on your comment about editing "Active Views selected defaults" ? I believe you are referring to my creation of TWO separate default sets for 1/2" scale for a plan AND a 3D view. The reason I did this was more about Layer Control with Electrical Fixtures turned ON or OFF, such as Wall mounted lights that clutter up a plan view when there are outlets below.

 

Thanks for any additional advice or clarification.

Link to comment
Share on other sites

Please sign in to comment

You will be able to leave a comment after signing in



Sign In Now
 Share

  • Member Statistics

    32647
    Total Members
    9156
    Most Online
    pewufilo
    Newest Member
    pewufilo
    Joined
  • Similar Content

    • By FT2design
      Automatically generated schedules…items that are added to a cabinet box such as a wall oven or lavatory show up in the schedule but I cannot seem to edit/control the name like I can with a free-standing item like a toilet or fridge. I have tried opening the cabinet dialogue box for that item to alter the individual component data so that the output in my schedule says what I need it to, but aside from renaming the cabinet label and assigning the cabinet as a plumbing fixture I don’t seem to be able to have the right control. Can anyone point me to a tutorial or reference a topic where this is covered? I keep chasing my tail searching for any tips and can’t find anything specific to my issue.
    • By gravattedesign
      My Note Label symbols are scaling larger than the layer font for the note text. This causes schedules to come in much larger when dropped into Layout. Schedules are created in a CAD DETAIL page in the PLAN file then dropped onto a layout page at the same scale as the drawing view the notes are linked. Please help with this anomaly. I have included a PDF with Screen shots of a sample layout page, Schedule and Layer settings.
       
      Thank you for anyoone who may be able to shed some light on this issue.
      22-0110-CHIEF ISSUES-GDS-Schedule Note scaling in layout.pdf
    • By decorators3
      Hi
       
      I am working on a residential renovation project
       
      The current house is a standard one level 40 x 24 with have a full 8' finished basement (not walk out) with L stairs to main floor . Exterior walls are Siding 4 and will follow upwards with the same
      The client has requested the following  revisions
      redesign main floor layout 
      change main floor from 8' to 9' ceilings
      add second level with 8' ceilings
      12/12 gable roof pitch with storage room and dormers
       
      I have done the revisions  but how do I note the added one foot to the main floor on my drawings for an engineer to sign of on to get the city building permit 
       
      Thanks in advance
       
      Levina
       
       
       
       
    • By BlackDiamond
      Hi,
      I'm trying to update my electrical schedule with all the fixtures I'm using on a plan. Some of the electrical symbols require a wall to be able to be placed on the plan.
      How can I get a copy of the symbol to place in my schedule without having to add a wall to do it?
      Thanks
    • By DRyeHD
      I'm looking for input on how to best use schedules in my .pln file and on my layout pages.  Per my screenshots, I have created several note schedules.  They are on separate CAD Details in my .pln template.  I have copied and pasted them to my .pln for reference.
       
      I try to put the applicable schedule on the layout page that it corresponds to so tradesmen don't have to reference just one notes page.  The preliminary note schedule is used just for preliminary work; likewise, the roof notes on the roof plan layout page, site notes on the site plan layout page, and remodel notes on remodel layout page.  The floor plan layout page usually contains the construction, plumbing, HVAC, cabinet, and trim note schedules.
       
      Is there a way to place the note schedules on the applicable pages of my layout template?  This would eliminate opening each CAD Detail and sending it to a layout page each time I work on a new layout for a specific plan.
       
      If there is not a way to have the note schedules on my layout template pages (before I save it as a specific customer layout), is there a more efficient way than what I am currently doing?
       
      Thanks in advance for your input.