HumbleChief Posted October 15, 2018 Share Posted October 15, 2018 I created a false, second floor to accommodate some unique framing and it worked out OK but it also puts my true second floor windows on floor 3 in the schedule. Is there a way to change that notation in the schedule to read floor 2 instead of floor 3? Link to comment Share on other sites More sharing options...
BrownTiger Posted October 15, 2018 Share Posted October 15, 2018 Create two schedulers for windows one for each floor, uncheck Include objects for all floors, thus limit one sched to floor 1 other to floor 3. Now you can place both hiding true floor #. Floor 1 Floor2 Sched 1 Sched3 Link to comment Share on other sites More sharing options...
MarkMc Posted October 15, 2018 Share Posted October 15, 2018 Or create custom OIP field Flr, group select windows and make that 2nd floor, show that column in schedule instead of Chief for floor. Link to comment Share on other sites More sharing options...
HumbleChief Posted October 16, 2018 Author Share Posted October 16, 2018 Sorry for bailing on this thread - swamped right now but appreciate the help. I ended up placing solid filled text over the numbers in the schedule. Pretty weak band-aid but had to get it done quick... Link to comment Share on other sites More sharing options...
Recommended Posts
Please sign in to comment
You will be able to leave a comment after signing in
Sign In Now