Adam_Gibson Posted February 9, 2021 Share Posted February 9, 2021 Suddenly I'm finding that when I build a new foundation based on the 1st floor, its walls are 4" outside the 1st floor. In this case the foundation is a pony wall with the lower wall an 8" concrete stem wall and the upper wall 4" concrete stem wall plus 4" brick facade. Rather than aligning with the exterior of the wall above, it seems to be aligning the main layers. Did I hit a switch or something? I don't recall this issue previously. Link to comment Share on other sites More sharing options...
SNestor Posted February 9, 2021 Share Posted February 9, 2021 Make sure you place the brick veneer into the main layer of the foundation wall. Your walls above are aligning to the "main layer". 1 Link to comment Share on other sites More sharing options...
Adam_Gibson Posted February 9, 2021 Author Share Posted February 9, 2021 That's it, Steve. Thank you. I could have racked my brain on this! Link to comment Share on other sites More sharing options...
Michael_Gia Posted February 9, 2021 Share Posted February 9, 2021 I think the real question is where your carpenters are placing the sill plate. This determines where your floor is built, which provides the ledge for your brick veneer, air space etc… My brick veneer usually overhangs past the foundation by at least 5/8”. But, of course this means you have to be careful that you dimension to the right layer if you want your exterior dimension of your foundation to agree with the floors above. (If you want to get picky) Link to comment Share on other sites More sharing options...
sarasa Posted March 9, 2021 Share Posted March 9, 2021 Well, the placement of the sill plate is also a really ... important point in this case. However, I guess it is not the first thing that you might think about. The fact that the veneeroverhangs past the foundation by at least 5/8'' is really great, however it might not always workout. It also depends on the facade. When I actually wanted to renovate the facade on my own house, I was too busy, so I called for the services of https://cprfacadeupgrades.com.au. They have done the job really quick and they had no questions regarding this subject. Link to comment Share on other sites More sharing options...
NRST8TRKR Posted March 10, 2021 Share Posted March 10, 2021 One more fly in this ointment. Here we have to extend exterior sheathing past and nail to sill plate so the outside of the sheathing of my framed wall has to line up with the outside of the brick on the foundation. Have a great Thursday,Ken Link to comment Share on other sites More sharing options...