robdyck Posted September 16, 2020 Share Posted September 16, 2020 Does anyone know how or where one could set different rebar options for different types of walls, or is the components tab the only place to do this? Example: I have retaining walls that require far more rebar than my default foundation walls. And unfortunately, one cannot copy a component AFAIK. Side question: is there a simple automatic way to get no. 4 rebar to report as 10M in a material list? And no. 5 as 15M etc. Link to comment Share on other sites More sharing options...
DzinEye Posted September 16, 2020 Share Posted September 16, 2020 For size in mm just type it in... or is that not automatic enough? Sorry if that's no help...I am no Chief 'materials' expert what-so-ever ... Link to comment Share on other sites More sharing options...
robdyck Posted September 16, 2020 Author Share Posted September 16, 2020 25 minutes ago, DzinEye said: I am no Chief 'materials' expert what-so-ever Thanks for trying Mark. I figured out how to add a formula to the automatic rebar counts that calculates the increased amount needed ...and some other components like rebar 'L's from footing to wall really quickly. Next Question: how do I copy components from one wall to another? Link to comment Share on other sites More sharing options...
dskogg Posted September 17, 2020 Share Posted September 17, 2020 15 hours ago, robdyck said: Thanks for trying Mark. I figured out how to add a formula to the automatic rebar counts that calculates the increased amount needed ...and some other components like rebar 'L's from footing to wall really quickly. Next Question: how do I copy components from one wall to another? Rob can you share what you did? Very interesting Link to comment Share on other sites More sharing options...
robdyck Posted September 17, 2020 Author Share Posted September 17, 2020 Wall DBX, components, footing, create a component using the plus symbol, go through each available row as you see fit, apply a formula to the source object that will populate your desired result based on the wall length. AFAIK, you cannot copy component setting from one wall to another. Link to comment Share on other sites More sharing options...
aaronbaribeau Posted July 11, 2021 Share Posted July 11, 2021 Sorry, somewhat new here. Tried following the above, but not figuring it out. I have a pool wall that has rebar at 8" O.C. spacing. I'm using foundation walls to build the pool shell (unless somebody has a better idea, I'm open to any and all ideas), is there a way to change the material list calculation to be based on 8" O.C. spacing? Link to comment Share on other sites More sharing options...