Is there a way to call out a clean out location for a sewer line in Chief?


cbucks
 Share

Recommended Posts

Hi there,

 

Here's what I use for my plans as the 2-Way Clean Outs typically need to be 24" apart. I've seen different surveyors and architects use different symbols and labeling for clean outs, the main objective here is to make sure that whatever symbol you use is in a drawing legend and/or clearly labeled directly on the plan. Hope this helps.

CAD W LABEL - NEW 2-WAY CLEAN OUTS.calibz

 

PS - I guess I should be clear that this is what I use for exterior clean outs (outside in yard). There are also interior clean outs for which I use an access panel with label, depending on the project scope.

  • Upvote 1