Hello,
When I ask Chief to build the foundation based off of the 1st floor, the foundation main layer (6" Stem wall) never lines up with the 1st floor main framing layer (plate).
When I use the "align with wall above" tool - the foundation shifts so the stem wall lines up with the edge of the veneer - in this case brick.
I'm in Oklahoma, and we typically center the stem wall on the footing and use the footing for a brick ledge.
My work around has been to copy the dimensions from the first floor and paste them onto the foundation and then manually move the walls around so the stem wall lines up with the outside of the framing layer.
Does anyone know how I can set up the foundation to build this way?
I have attached the plan I'm working on. I also copied the dimensions from the first floor so you can see where I'd like the stem walls to line up.
Any help is much appreciated,
Joe / OKC
Bennett,_Michael_1-10-19.plan