Ed_Orum Posted March 3, 2021 Share Posted March 3, 2021 The screenshot shows the concrete slab in the bump out floating above the rest of the basement floor. How do I get the slab to be in the correct position (resting on the footings like the rest of the basement) but still leave the landing floor above in the correct elevation? Plan is attached. Thanks in advance, Lane Raised Ranch 5230 Plan File.plan Link to comment Share on other sites More sharing options...
steve_stuart Posted March 3, 2021 Share Posted March 3, 2021 Counter intuitive but raise the height of the ceiling in that "Under Stair Storage" room and it will lower the slab. Link to comment Share on other sites More sharing options...
Ed_Orum Posted March 3, 2021 Author Share Posted March 3, 2021 thats it, Thanks! Link to comment Share on other sites More sharing options...