Framing adjustment help.


HillsBuild
 Share

Recommended Posts

Hi All!  New here and new to chief architect.  I'm still learning and hoping to get some help.  

 

I am not an architect.  I use this software for rough designs on remodels.  

 

I'm working on a basement buildout that we will not be finishing the ceiling on.  My wall framing is being constructed like the picture with triple studs under all of the floor joists.  Is there a way to easily fix this other than adjusting each wall one stud at a time? 

Screenshot 2025-09-02 at 10.08.35 AM.png

Link to comment
Share on other sites

Alright.... Took a minute BUT all of your floor joists are drawn as a BEAM instead of a joist. The software is assuming that you want a stud pack there to transfer load. If you change your beams to joists and reframe the wall it should frame normally.